- Location
- Grand Junction, CO
Last week we replaced a panel of track in a road crossing and I decided to take a few pic of the process. Thought I'd share with you folks how that went.
The crossing here was holding a lot of water, which isn't good... the ties were about 1/3 a thick as they should have been, the track was sinking in the crossing and plows of the trains were starting to hit the concrete crossing planks, to the point that concrete was being broken out and steel holding it together was bent and broken.
Myself and my laborer built the panel in a day and a half, which is 40' long, using 24, 10' ties and weighs almost 6,000 pounds. We loaded it on 2 push cars, then hauled the panel several miles down the track with my hyrail truck and unloaded the panel with the backhoe at the crossing, the day before we tore apart the crossing.
We closed the crossing on Wednesday at 6:00am started at 6:15 had the track for 3 hours before the next train. In that time we had to cut the rail in 4 places, yank the old panel out, clean out all the nasty dirt/mud/water, put the new panel back in, bolt it up, dump new ballast/rock, spread it out, surface the track with 2 on-track machines and clear up for 3 trains. The crossing planks were still out, so after those 3 trains passed, we placed the planks, then the welders went to work, making sure the planks stayed put. After that, a little clean up and the road crossing went back in service, 3 hours ahead of schedule.
Here's pics of the process as it went on... I didn't get any pics of the concrete planks going in and out... I was working.
The crossing here was holding a lot of water, which isn't good... the ties were about 1/3 a thick as they should have been, the track was sinking in the crossing and plows of the trains were starting to hit the concrete crossing planks, to the point that concrete was being broken out and steel holding it together was bent and broken.
Myself and my laborer built the panel in a day and a half, which is 40' long, using 24, 10' ties and weighs almost 6,000 pounds. We loaded it on 2 push cars, then hauled the panel several miles down the track with my hyrail truck and unloaded the panel with the backhoe at the crossing, the day before we tore apart the crossing.
We closed the crossing on Wednesday at 6:00am started at 6:15 had the track for 3 hours before the next train. In that time we had to cut the rail in 4 places, yank the old panel out, clean out all the nasty dirt/mud/water, put the new panel back in, bolt it up, dump new ballast/rock, spread it out, surface the track with 2 on-track machines and clear up for 3 trains. The crossing planks were still out, so after those 3 trains passed, we placed the planks, then the welders went to work, making sure the planks stayed put. After that, a little clean up and the road crossing went back in service, 3 hours ahead of schedule.
Here's pics of the process as it went on... I didn't get any pics of the concrete planks going in and out... I was working.